10 day grace period on my 180 day server 2012 evaluation?

$
0
0

Question

I just installed an eval copy of windows server 2012 (datacenter) core.

It says its a 180 evaluation, but checking the licensing info I see this:

enter image description here

Is this different for core installs than GUI because I have used the same iso to do full GUI installs and it always gives me 180 days.

I should also add when downloading the trail I was not provided a license key.

Asked by red888

Answer

You never activated it online…you have to do that to allow for the full 180 days.

For all editions, you have 10 days to complete online activation, at
which point the evaluation period begins and runs for 180 days.

http://technet.microsoft.com/en-us/library/jj574204.aspx